  • Develop plan and next steps for transitioning EDSC to NGAP 1.1

Discussion Items

The following is high level overview of what needs to happen to transition EDSC to NGAP 1.1

  1. Send NCIS an overview of application. (Node/Rails/NLP/DB)
  2. Docker file
  3. Ensure NCIS team has access to build and deploy plans in Bamboo
  4. NCIS team does testing in NGAP SIT
  5. Create apps in NGAP Prod for App Sit/UAT/Prod
  6. Distribute keys as needed
  7. NCIS team - GO!

EDSC will need to move through the following environments to demonstrate a high level of confidence that the transition to NGAP Prod will be successful and smooth.

  • ECS SIT - Internal only for testing
  • ECS UAT - Internal
  • ECS Prod - Public

Tim has been added to the EDSC Slack channel and we are all committed to helping each other, communicating, raising issue early, documenting everything, and driving the effort of transitioning to NGAP 1.1 to completion. This will spill over into Sprint 3 of PI7.

Action items

  • Timothy Goff to confirm if EDSC and CMR can use the same DB or need to migrate/transfer
  • Timothy Goff to provide guidance on clusters for EDSC
  • Timothy Goff to determine current EDSC scaling (and other) config and how it maps to new config
  • user-4b40c user-c83ea to work with Tim to figure out NLP jar file issue
  • user-4b40c to create SIT app. user-f66c7 to create UAT/Prod app
  • user-c83eauser-4b40c update NLP URLs after transition
  • Timothy Goff confirm downtime associated with transitioning. We need a deployment/roll-out plan and what should be expected by app owners, dev teams, and end users.
  • Timothy Goffuser-396c2 to break down transition ticket ( NGAP-1996 - Getting issue details... STATUS ) into smaller tickets. We need detailed traceability!   NGAP-2145 - Getting issue details... STATUS   NGAP-2146 - Getting issue details... STATUS
  • user-396c2 to confirm plan for sprint 3 completion (EDSC SIT to NGAP 1.1 Prod)