ASDC | |||||
---|---|---|---|---|---|
Name | Position | Name | Position | ||
Walt Baskin | walter.e.baskin@nasa.gov | Granule-level metadata at ASDC | Karen Dragon | karen.c.dragon@jpl.nasa.gov | JPL PREFIRE Systems Engineer |
Susan Kizer | susan.h.kizer@nasa.gov | ASDC Group lead. | Erin Hokanson Wagner | ephokanson@wisc.edu | PREFIRE Data System Manager |
Lindsay Parker | lindsay.parker-1@nasa.gov | Former ASDC group lead | Karen Michael | karen.a.michael@nasa.gov | GSFC, ESDIS |
Peter Piatko | peter.j.piatko@nasa.gov | Lead developer at ASDC | Mary White | mary.l.white@jpl.nasa.gov | PREFIRE Project Manager |
Christopher Howard | christopher.k.howard@nasa.gov | Developer at ASDC | Brian Drouin | brian.j.drouin@jpl.nasa.gov | PREFIRE Project Scientist |
Wei Zhang | wei.zhang-1@nasa.gov | Developer at ASDC | Steven Dutcher | SIPS | |
Susan Haberer | susan.j.haberer@nasa.gov | Metadata team lead | Stephanie Jones | JPL PREFIRE V & V | |
Hazem Mahmoud | hazem.mahmoud@nasa.gov | Earth Scientist | |||
Caroline Downey | caroline.r.downey@nasa.gov | ASDC Collection level metadata coordinator |
Date | Event | Responsible | Location | Notes |
1-Dec-2023 | SRB membership letter | PSO | OneSpan esign | |
18-Dec-2023 | Safety Review | JPL | Webex | |
3-Jan-2024 | Deliver GP documents to SRB | Project | mail in | |
4-Jan-2024 | Institutional Readiness To Proceed (to ORR/MRR) | 8X | JPL / Webex | |
9-Jan-2024 | SRB Readiness Telecon (SRB chair, ESD, PM) | SRB | ESD Teams | |
16-Jan-2024 | CoFR 3, includes ITL and TAYFE | Project | JPL / Webex | |
17-Jan-2024 | SRB Chair Readiness Assessment | SRB | mail in | |
17-Jan-2024 | Institutional Risk Review | 8X | JPL / Webex | |
19-Jan-2024 | SRB Kickoff Meeting | SRB | ? | SRB only, not project |
1-Feb-2024 | ORR | SRB | JPL / Webex | |
2-Feb-2024 | SRB Snapshot Report | SRB | mail in | 1 page, expected in 24 to 48 hours |
7-Feb-2024 | Snapshot Report Briefing | ESD | ESD Teams | |
14-Feb-2024 | Mission Integration Readiness Review | RL | RL Zoom | |
16-Feb-2024 | SRB ORR Board Report | SRB | mail in | |
27-Feb-2024 | Transportation Planning Review | Project | Webex | JPL Type 3, project convened, Div38 led |
5-Mar-2024 | Safety Survey | JPL | Webex | 3 weeks prior to shipment of CubeSats from BCT to RL Long Beach |
7-Mar-2024 | Delta CubeSats Pre Ship Review and MRR | IRT | JPL / BCT / Webex | |
16-Mar-2024 | Launch Processing Readiness Review | RL | RL Zoom | |
18-Mar-2024 | DMC (8X) | 8X | JPL / Webex | |
20-Mar-2024 | Pre-brief to Flight/ESSP | Schwinger and Law | ||
25-Mar-2024 | Pre-brief to ESD Director | ESD | ESD Teams | St. Germain |
25-Mar-2024 | CoFR (launch) | OCE | JPL / Webex | |
27-Mar-2024 | Final Mission Analysis Review (RL led) | RL | RL Zoom | |
28-Mar-2024 | KDP-E (dPMC) | NASA ESD | NASA and Teams? | |
2-Apr-2024 | Ship from RL Long Beach | RL | RL LB | |
24-Apr-2024 | Ship from BCT | ESSP | BCT | |
14-May-2024 | Launch Readiness Review #1 (RL led) | RL | RL Zoom | |
15-May-2024 | Launch #1 | RL | RL Mahia | FM2 |
2-Jun-2024 | Launch Readiness Review #2 (RL led) | RL | RL Zoom | |
3-Jun-2024 | Launch #2 | RL | RL Mahia | FM1 |
19-Jun-2024 | PLAR | IRT | JPL / Webex | |
Dates are TBD |