Sprint Review | Date | Demo Schedule | Sprint Health (Current Active Sprint) |
---|---|---|---|
21.1.3 |
| Pulled in bug tickets and CSDAP data download user experience. Didn't finish the CSDAP work. |
Question | Response | Dashboard Gadget | |
---|---|---|---|
1 | Did the team complete all of last sprint Goals? Explain any goals that did not complete. |
| |
2 | Does the team have any blockers? |
| Blocked Tickets |
3 | Are there any dependencies that are delayed for the last sprint? | Delayed Dependencies | |
4 | What work related to PI Objectives will you be working on in the upcoming sprint? | Upcoming PI Work OBJECTIVES: | |
5 | Which objectives are (on/off) track for the PI, or moving (faster/slower) than expected? | We are a little more than 2 weeks behind, but we only have 1 EDSC ticket scheduled for sprint 5 so I think we can still finish on time. (April 2nd). |