Sprint Health (Current Active Sprint)
08 Mar 2021
Data Use PI 21.1 Demo Schedule
Pulled in bug tickets and CSDAP data download user experience. Didn't finish the CSDAP work.
Did the team complete all of last sprint Goals? Explain any goals that did not complete.
We are a little more than 2 weeks behind, but we only have 1 EDSC ticket scheduled for sprint 5 so I think we can still finish on time. (April 2nd).