Set goals, objectives or some context for this meeting.
Discussion items
EDSC and NLP are deployed to SIT 1.1. Most changes were procfile changes.
NLP port is hardcoded. This port should be configurable as an env variable.
Tim recommends rolling EDSC SIT to NGAP 1.1 Prod. NGAP UAT doesn't have 1.1.
Proposed schedule
10/23 - EDSC/NLP SIT to NGAP Prod
Deploy updated NGAP API to prod
Create apps
Merge EDSC/NLP code changes
Update NLP urls
Dockerfile
Procfile
Intermediate script
Deploy EDSC/NLP SIT to NGAP 1.1 Prod
Request updated DNS entry for EDSC SIT
10/25 - EDSC UAT to NGAP Prod
Backport of EDSC/NLP code changes
Deploy EDSC/NLP UAT to NGAP 1.1 Prod
Request updated DNS entry for EDSC UAT
11/1 - EDSC Prod to NGAP Prod
Regular PM rollout of EDSC Prod to NGAP 1.1
Request updated DNS entry for EDSC Prod
Action items
Timothy Goff - Determine who can create an app in NGAP. Probably should be Ops team.
Determine if someone other than app creator can refresh tokens
NGAP/NCIS team member will create apps and set Ops/EDSC team members as admins so they can refresh tokens.
In addition to all of the apps currently created on NGAP 1.0, the NLP app will need nlp-sit and nlp-uat so that we can have a testing environment/app for NLP.
SIT and UAT are done. Prod will be done next sprint.
Once apps are created, provide app names to user-c83ea
Timothy Goff - create EI ticket for switching DNS entries for SIT/UAT/Prod (when each env is ready)
user-c2913 - get performance standards for EDSC from Doug