Did the team complete all of last sprint Goals? Explain any goals that did not complete.
Weren't able to check off any goals because the SIT DNS never got updated by the Platform team. That work is in progress, but failed verification late in the sprint. As of 11/28 the SIT DNS does not resolve. This will be our top priority early in sprint 5.
Update Access SIT DNS to point to new application
Update CMR to use new Access app for landing pages
2
Does the team have any blockers?
Updating platform facet is currently blocked. Waiting on timeline from UMM team.
3
Are there any dependencies that are delayed for the last sprint?
Waiting on DNS update for Access SIT. We will need the same work done for UAT and Prod when that is ready.
Updating platform facet is currently blocked. Waiting on timeline from UMM team.
4
What work related to PI Objectives will you be working on in the upcoming sprint?
Adding STAC support for granule searches
Updating CMR to use Access App
Continue promoting Access to upper environments
OBJECTIVES:
5
Which objectives are (on/off) track for the PI, or moving (faster/slower) than expected?
If Platform delivers on DNS updates in a timely manner, the Access application work should complete on time. If there are even slight delays, that may result in work spilling over into the IP sprint.