Time | Item | Who | Notes |
---|
| Admin | Tim | - Earthdata Wiki Space for collaboration
- Coordination Schedule
- Boon: CDR rescheduled for Mid may, need to show plan/strategy for ingest.
- For CDR, sufficient to show high-level description of ingest/handoff
- EIS testing and system testing, end-to-end testing with Metadata in October/November timeframe
- Boon: attempt a test data delivery, L0 data may be ready, possibly in June/July timeframe
- Need to speak with Erin Wagner
- delivery cadence anticipated to be daily.
- 4 deliveries daily planned from instrument to processing
- 60 Days until next meeting
|
|
| ASDC | |
|
| PREFIRE | - Requesting best practice
- What is the preferred ingest protocol?
- Lindsay - Karen Brown will provide keys for drop box access. We will want sample files at ASDC.
- Boon: can we look at sample data?
- PREFIRE may want additional viewer/sub
|
|
|
| - Lindsay: Some of the granule sizes were noted to be too large. The ICD says that L2B flux granules are 20.5GB. Granules are recommended to be 4GB
- @Boon Lim will investigate
- Larger files slow ingest process
|