ASDC PREFIRE Mission Support Homepage

Documents

  1. PREFIRE ICD 423-ICD-026_ICD_between_PREFIRE_ASDC_DAAC_RevA.docx

Resources

  1. netCDF ToolsUI (Unidata/UCAR) - UDunits to format units in the netCDF files
  2. CF Compliance checker
  3. HDF Product Designer
  1. Email/PDF: Assignment of the missions to ASDC by ESDIS
  2. Doc: 90-day plan document for ESDIS (within 90-days of the assignment) 
  3. Doc: Data Management Plan (DMP) between the data provider (Science Team's Data Manager) and ASDC
  4. Doc: Interface Control Document(s) (ICDs) between various entities involved
  5. Meeting: Set up regular (weekly/monthly) meetings with the science team:
    1. discuss data/file format, file naming convention,
    2. metadata content/format (UMM-C for collections, UMM-G for granules),
    3. ingest/delivery
    4. Distribution services/APIs/Subsetters
    5. Visualization: GIBS/WorldView
    6. NRT (near-real time) requirements
    7. End-to-end testing 
  6. Support the Science Team for various reviews:
    1. PDR (Preliminary Design Review),
    2. CDR (Critical DR),
    3. ORR (Operational Readiness Review)
  7. Support the Science Team for Early data access and Early adopters workshops
    1. Limited access to certain granules on CMR/EDSearch based on user-list 

DateEventResponsibleLocation Notes
11-Oct-2023Mission Integration Working Group (MIWG)RLRL Zoom
1-Nov-2023Mission Specific Design ReviewRLRL LB / RL Zoom
7-Nov-2023SMD/JPL Quarterly ReviewSMDJPL / Webex
23-Nov-2023Monthly Management Report (4th Thurs)Projectmail in
1-Dec-2023SRB membership letterPSOOneSpan esign
18-Dec-2023Safety ReviewJPLWebex
12-Dec-2023Project Status Report due (2nd Tues)Projectmail in
13-Dec-2023SRB Kickoff MeetingSRB?SRB only, not project
14-Dec-2023Send invitation to SRB and PresentersProjectmail in
9-Jan-2023Transportation Planning ReviewProjectWebexJPL Type 3, project convened, Div38 led
18-Dec-2023Send invitation to othersProjectmail in
28-Dec-2023Monthly Management Report (4th Thurs)Projectmail in
3-Jan-2024Deliver GP documents to SRBProjectmail in
4-Jan-2024Institutional Readiness To Proceed8XJPL / Webex
8-Jan-2024SRB Readiness Telecon (SRB chair, ESD, PM)SRBESD Teams
15-Feb-2024Delta CubeSats Pre Ship ReviewIRTJPL / BCT / Webex
9-Jan-2024Project Status Report due (2nd Tues)Projectmail in
10-Jan-2024SRB Chair Readiness AssessmentSRBmail in
16-Jan-2024CoFR 3, includes ITL and TAYFEProjectJPL / Webex
17-Jan-2024Institutional Risk Review8XJPL / Webex
18-Jan-2024ORR-MRR Dry Runs startProjectJPL / Webex
23-Jan-2024ORR/MRR Dry Runs endProjectJPL / Webex
24-Jan-2024ORR-MRR draft slides to SRBProjectmail in
25-Jan-2024Monthly Management Report (4th Thurs)Projectmail in
26-Jan-2024ORR-MRR final slides to SRBProjectmail in
31-Jan-2024ORR-MRR Day 1SRBJPL / Webex
1-Feb-2024Mission Integration Readiness ReviewRLRL Zoom
1-Feb-2024ORR-MRR Day 2SRBJPL / Webex
2-Feb-2024SRB Snapshot ReportSRBmail in1 page, expected in 24 to 48 hours
6-Feb-2024Snapshot Report BriefingESDESD Teams
6-Feb-2024SMD/JPL Quarterly ReviewSMDJPL / Webex
16-Feb-2024SRB ORR-MRR Board ReportSRBmail in
21-Feb-2024DMC (8X)8XJPL / Webex
22-Feb-2024ESSP pre-briefESSPESSP TeamsESSP-Law, maybe merge with ESD pre-brief
22-Feb-2024Monthly Management Report (4th Thurs)Projectmail in
27-Feb-2024ESD pre-briefESDESD TeamsKaren St. Germain.  Is this req'd for a dPMC?
2-Mar-2024Launch Processing Readiness Review #1RLRL Zoom
5-Mar-2024Safety SurveyJPLWebex3 weeks prior to shipment of CubeSats from BCT to RL Long Beach
11-Mar-2024CoFR (launch)OCEJPL / Webex
12-Mar-2024Project Status Report due (2nd Tues)Projectmail in
15-Mar-2024SMD DAAP pre-briefSMD DAAPSMD TeamsPE A Whitehurst presents to DAAP Wanda Peters.  Is this req'd for dPMC?
16-Mar-2024Launch Processing Readiness Review #2RLRL Zoom
21-Mar-2024Monthly Management Report (4th Thurs)Projectmail in
26-Mar-2024Ship from BCTESSPBCT
27-Mar-2024Final Mission Analysis Review (RL led)RLRL Zoom
28-Mar-2024KDP-E (dPMC)NASA ESDNASA and Teams?
2-Apr-2024Ship from RL Long BeachRLRL LB
9-Apr-2024Project Status Report due (2nd Tues)Projectmail in
25-Apr-2024Monthly Management Report (4th Thurs)Projectmail in
30-Apr-2024Launch Readiness Review #1 (RL led)RLRL Zoom
1-May-2024Launch #1RLRL Mahia
14-May-2024Project Status Report due (2nd Tues)Projectmail in
14-May-2024Launch Readiness Review #2 (RL led)RLRL Zoom
15-May-2024Launch #2RLRL Mahia
23-May-2024Monthly Management Report (4th Thurs)Projectmail in
11-Jun-2024Project Status Report due (2nd Tues)Projectmail in
19-Jun-2024PLAR8X?JPL / Webex
LEVELPRODUCTFILENAME (COLLECTION)
L0Radianceprefire_01_payload_tlm_2022_07_15_18_53_21.binPROJECT_SATELLITE ID_PRODUCT_PRODUCT_YYYY_MM_DD_HH_MM_SS.bin/csv
TLMTelemetryprefire_01_bus_tlm_2022_07_15_18_53_21.csv
ORBSatellite orbital dataprefire_01_2022_07_15_18_53_21.tlePROJECT_SATELLITE ID_YYYY_MM_DD_HH_MM_SS.tle
L1ACalibrated RadiancePREFIRE_SAT_1A-RAD_P01_R01_20220715185321_00001.nc
L1BGeolocated RadiancePREFIRE_SAT1_1B-RAD_P01_R01_20220715185321_00001.ncPROJECT_SATELLITE ID_PRODUCT_PRODUCT VERSION_COLLECTION-LEVEL VERSION_YYYYMMDDHHMMSS_GRANULE ID.nc




L2BFluxPREFIRE_SAT1_2B-FLX_P01_R01_20220715185321_00001.nc
L2BSurface PropertiesPREFIRE_SAT1_2B-SFC_P01_R01_20220715185321_00001.nc
L2BCloud MaskPREFIRE_SAT1_2B-MSK_P01_R01_20220715185321_00001.ncSAT1 = PREFIRE Cube Satellite 1
L2BAtmosphere PropertiesPREFIRE_SAT1_2B-ATM_P01_R01_20220715185321_00001.ncSAT2 = PREFIRE Cube Satellite 2
L2BCloud PropertiesPREFIRE_SAT1_2B-CLD_P01_R01_20220715185321_00001.nc




L3Geolocated RadiancePREFIRE_SAT1_3-RAD_P01_R01_20220715185321-20220724185321.ncPROJECT_SATELLITE ID_PRODUCT ID_PRODUCT VERSION_COLLECTION-LEVEL VERSION_YYYYMMDD-YYYYMMDD.nc
L3FluxPREFIRE_SAT1_3-FLX_P01_R01_20220715185321-20220724185321.nc
L3Surface PropertiesPREFIRE_SAT1_3-SFC_P01_R01_20220715185321-20220724185321.ncYYYYMMDD-YYYYMMDD = start date - end date of data collection
L3Atmosphere PropertiesPREFIRE_SAT1_3-ATM_P01_R01_20220715185321-20220724185321.nc
L3CloudsPREFIRE_SAT1_3-CLD_P01_R01_20220715185321-20220724185321.nc
L3Standard sorted climatologyPREFIRE_SAT1_3-SORTED_P01_R01_20220715185321-20220724185321.ncNecessary?
L3Sorted climatology - allskyPREFIRE_SAT1_3-SFC-SORTED-ALLSKY_P01_R01_20220715185321-20220724185321.nc

Sorted climatology - cloudyPREFIRE_SAT1_3-SFC-SORTED-CLRSKY_P01_R01_20220715185321-20220724185321.nc
L3Sorted climatology - clearPREFIRE_SAT1_3-SFC-SORTED-CLDSKY_P01_R01_20220715185321-20220724185321.nc




AUXMeteorologyPREFIRE_AUX-MET_P01_R01_20220715185221.nc
AUXSatellite DataPREFIRE_AUX-SAT_P01_R01_20220715185321.nc




SIM1BGeolocated RadiancePREFIRE_SAT1_1B-RAD_S00_R00_20220715185321_00001.ncPROJECT_SATELLITE ID_PRODUCT_PRODUCT VERSION_COLLECTION-LEVEL VERSION_YYYYMMDDHHMMSS_GRANULE ID.nc
SIM2BFluxPREFIRE_SAT1_2B-FLX_S00_R00_20220715185321_00001.nc
SIM2BSurface PropertiesPREFIRE_SAT1_2B-SFC_S00_R00_20220715185321_00001.nc
SIM2BCloud MaskPREFIRE_SAT1_2B-MSK_S00_R00_20220715185321_00001.nc
SIM2BAtmosphere PropertiesPREFIRE_SAT1_2B-ATM_S00_R00_20220715185321_00001.nc
SIM2BCloud PropertiesPREFIRE_SAT1_2B-CLD_S00_R00_20220715185321_00001.nc




SIM3Geolocated RadiancePREFIRE_SAT1_3-RAD_S00_R00_202207.ncSAT1 = PREFIRE Cube Satellite 1
SIM3FluxPREFIRE_SAT1_3-FLX_S00_R00_202207.ncSAT2 = PREFIRE Cube Satellite 2
SIM3Surface PropertiesPREFIRE_SAT1_3-SFC_S00_R00_202207.ncSAT1SAT2 = Both PREFIRE Cube Satellites (climatologies)
SIM3Atmosphere PropertiesPREFIRE_SAT1_3-ATM_S00_R00_202207.nc
SIM3CloudsPREFIRE_SAT1_3-CLD_S00_R00_202207.nc
SIM3Sorted climatologyPREFIRE_SAT1_3-SFC-SORTED_S00_R00_202207.nc




SIMAUXMeteorologyPREFIRE_AUX-MET_S00_R00_20220715185221.nc
SIMAUXSatellite DataPREFIRE_AUX-SAT_S00_R00_20220715185321.nc