Did the team complete all of last sprint Goals? Explain any goals that did not complete.
Related collections added to collection details panel.
The bulk of the platform facet work has been finished in EDSC, but there are still CMR changes that need to be merged before we can fully test. Waiting on CMR-7185 and CMR-7253 to be finished before we wrap up.
NPM updates are taking longer than expected.
UMM team to finish CMR tickets indicated below before we finish the EDSC work.
NPM update work is ongoing, but this is a major version change impacting the entire application, so it is taking a long time.
Document all EDSC URL parameters
Implement new platform facet structure
Update NPM libraries
Display related collections
2
Does the team have any blockers?
Platform type query search for more precise returns (EDSC-3211) blocked: