Date | Event | Responsible | Location | Notes |
1-Dec-2023 | SRB membership letter | PSO | OneSpan esign |
|
18-Dec-2023 | Safety Review | JPL | Webex |
|
3-Jan-2024 | Deliver GP documents to SRB | Project | mail in |
|
4-Jan-2024 | Institutional Readiness To Proceed (to ORR/MRR) | 8X | JPL / Webex |
|
9-Jan-2024 | SRB Readiness Telecon (SRB chair, ESD, PM) | SRB | ESD Teams |
|
16-Jan-2024 | CoFR 3, includes ITL and TAYFE | Project | JPL / Webex |
|
17-Jan-2024 | SRB Chair Readiness Assessment | SRB | mail in |
|
17-Jan-2024 | Institutional Risk Review | 8X | JPL / Webex |
|
19-Jan-2024 | SRB Kickoff Meeting | SRB | ? | SRB only, not project |
1-Feb-2024 | ORR | SRB | JPL / Webex |
|
2-Feb-2024 | SRB Snapshot Report | SRB | mail in | 1 page, expected in 24 to 48 hours |
7-Feb-2024 | Snapshot Report Briefing | ESD | ESD Teams |
|
14-Feb-2024 | Mission Integration Readiness Review | RL | RL Zoom |
|
16-Feb-2024 | SRB ORR Board Report | SRB | mail in |
|
27-Feb-2024 | Transportation Planning Review | Project | Webex | JPL Type 3, project convened, Div38 led |
5-Mar-2024 | Safety Survey | JPL | Webex | 3 weeks prior to shipment of CubeSats from BCT to RL Long Beach |
7-Mar-2024 | Delta CubeSats Pre Ship Review and MRR | IRT | JPL / BCT / Webex |
|
16-Mar-2024 | Launch Processing Readiness Review | RL | RL Zoom |
|
18-Mar-2024 | DMC (8X) | 8X | JPL / Webex |
|
20-Mar-2024 | Pre-brief to Flight/ESSP |
|
| Schwinger and Law |
25-Mar-2024 | Pre-brief to ESD Director | ESD | ESD Teams | St. Germain |
25-Mar-2024 | CoFR (launch) | OCE | JPL / Webex |
|
27-Mar-2024 | Final Mission Analysis Review (RL led) | RL | RL Zoom |
|
28-Mar-2024 | KDP-E (dPMC) | NASA ESD | NASA and Teams? |
|
2-Apr-2024 | Ship from RL Long Beach | RL | RL LB |
|
24-Apr-2024 | Ship from BCT | ESSP | BCT |
|
14-May-2024 | Launch Readiness Review #1 (RL led) | RL | RL Zoom |
|
15-May-2024 | Launch #1 | RL | RL Mahia | FM2 |
2-Jun-2024 | Launch Readiness Review #2 (RL led) | RL | RL Zoom |
|
3-Jun-2024 | Launch #2 | RL | RL Mahia | FM1 |
19-Jun-2024 | PLAR | IRT | JPL / Webex |
|
|
|
|
|
|
Dates are TBD |
|
|
|
|