  • EDSC and NLP are deployed to SIT 1.1. Most changes were procfile changes.
  • NLP port is hardcoded. This port should be configurable as an env variable.  EDSC-1661 - Getting issue details... STATUS
  • Tim recommends rolling EDSC SIT to NGAP 1.1 Prod. NGAP UAT doesn't have 1.1.
  • Proposed schedule
    • 10/23 - EDSC/NLP SIT to NGAP Prod
      • Deploy updated NGAP API to prod
      • Create apps
      • Merge EDSC/NLP code changes
        • Update NLP urls
        • Dockerfile
        • Procfile
        • Intermediate script
      • Deploy EDSC/NLP SIT to NGAP 1.1 Prod
      • Request updated DNS entry for EDSC SIT
    • 10/25 - EDSC UAT to NGAP Prod
      • Backport of EDSC/NLP code changes
      • Deploy EDSC/NLP UAT to NGAP 1.1 Prod
      • Request updated DNS entry for EDSC UAT
    • 11/1 - EDSC Prod to NGAP Prod
      • Regular PM rollout of EDSC Prod to NGAP 1.1
      • Request updated DNS entry for EDSC Prod

Action items

  • Timothy Goff - Determine who can create an app in NGAP. Probably should be Ops team.
    • Determine if someone other than app creator can refresh tokens
      • NGAP/NCIS team member will create apps and set Ops/EDSC team members as admins so they can refresh tokens.
    • In addition to all of the apps currently created on NGAP 1.0, the NLP app will need nlp-sit and nlp-uat so that we can have a testing environment/app for NLP.
      • SIT and UAT are done. Prod will be done next sprint.
    • Once apps are created, provide app names to user-c83ea
  • Timothy Goff - create EI ticket for switching DNS entries for SIT/UAT/Prod (when each env is ready)
    • EI-6694 - Getting issue details... STATUS  
    • EI-6695 - Getting issue details... STATUS
    • EI-6696 - Getting issue details... STATUS
  • user-c2913 - get performance standards for EDSC from Doug

2 Comments

  1. user-c2913

    Talked with Doug and from a performance standards perspective we just need to show that things are operating in line with current performance. I have gathered load times for various pages in all environments and am comparing them to 1.1 deployments to ensure things are in line.

  2. user-c2913

    One more update to this timeline... we are rolling out UAT on 11/1 as part of our normal PM and Prod will be deployed to 1.1 on 11/15.